Project information
Project: PERALADA WWTP
Country: Spain
Location: Peralada (Girona)
Year: 2019
Flow rate: 2m3/h
Equipment: ScrewTech®Nw80.215 (2 units) + ScrewTech®Nw81.215 (1 units).
Netwater Technology, has carried out the installation of THREE screw conveyor for sludge transport:
The main objective of this installation was to achieve:
-Change the current technology of transport of sludges that they had installed by means of screw pump, for a system of screw conveyor.
Netwater Technology, through this installation, has managed to meet the needs of our client, has installed a more efficient transportation system, which eliminates 100% frequent jams that had the previous technology.
The THREE screw conveyors were designed base don the dimensionjs of the existing construction. For example, in the vertical screw conveyor, intermediate supports have been designed according to the support points provided by the iron structure that supports the storage tank.
We provide some images for you to see the scope of this project.